The following streets will be closed Monday, June 16th - Wednesday, June 18th and Monday, June 23rd - Thursday, June 26th between the hours of 7:00am - 4:00pm:
Boright St (N 4th St to 500’ East)
Davis St (S 2nd St to S 3rd St)
Lynn St (Dakota Ave to Jay St)
N 3rd St (Bridge St to Swan St)
N 3rd St (Swan St to Oak St)
Scott Ter
Todd St
Crews will perform a full-depth reclamation of the bituminous surface. A full-depth reclamation grinds up the existing bituminous pavement and incorporates it into the aggregate base. This significantly improves the quality of the aggregate base leading to a longer-lasting bituminous surface while lowering the overall cost by recycling the materials on-site.
This work is in preparation of new bituminous pavement to be installed in July. Temporary “No Parking” signs will be installed.
Questions? Please call Public Works & Facilities Manager, Joel Schmidt at 507-593-8378.