Second Street North Reconstruction Project

Project Details



Description


Work includes reconstruction of sanitary sewer, water main, storm sewer, sewer and water end services, bituminous surfacing, concrete curb and gutter, sidewalk, driveway aprons, and surface restoration (project area map, below).

Schedule


  1. Phase 1: July 24th (approx).  Area includes; Maple Street, Church Street, Grove Street, and northernmost two blocks of Second Street.
  2. Phase 2: August 14th (approx).  Area includes: Oak Street, Swan Street, and southernmost three blocks of Second Street.

Project Documents

Benefit Appraisal
Bid Award Letter
Project Area Map



Contact Information


Questions about this project?  Contact Jasper Kruggel at jkruggel@cityoflesueur.com or (507) 593-8312.

Project Update 8/10/17

Oak Street, from North Second to the alleyway, will be closed until further notice (most likely until project completion). Questions can be directed to Owen Todd, Project Manager, at (507) 625-4171.